As the Sutton Road Improvement Project continues, the Hamilton County Engineer’s Office announced the next portion of Sutton, between Eversole Road and Four Mile Road, will be closed from Wednesday, May 27, through Wednesday, June 3. 

The closure will allow for pavement repairs and resurfacing in this section of roadway. The detour is Sutton Road to Salem Road, then to Eversole Road, then back to Sutton and vice versa.

Sutton Road, between Eversole Road and Kellogg Road, which is currently under construction, will REOPEN on May 27.

Despite the recent wet weather, the repaving work on Sutton is still on schedule for completion by late June.